Project Location: Bandar Imam Khomeini
Contractor: Omran Sanat Abadan
Installed and connected electrical control panels and circuits for rail operation systems.
Performed grounding and insulation resistance tests to ensure compliance with safety standards.
Maintained and upgraded overhead power lines supplying power to rail systems.
Conducted insulation resistance testing for high-voltage cables and equipment.
Inspected power lines for defects, corrosion, and environmental damage.
Recommended technical upgrades to enhance system reliability and safety.
Client: Sepehr Morvarid Khalij Fars Company
Consultant: Arvand Zahab Designers Consulting Engineers
Contractor: Omran Sanat Abadan Company
Designed and installed temporary power supply systems for construction equipment.
Conducted risk assessments for electrical hazards and developed mitigation plans.
Collaborated with structural engineers to integrate safe electrical components.
Designed and installed safety monitoring systems for high-voltage networks.
Evaluated protection systems, including circuit breakers and surge protectors.
Provided training on safe electrical practices and created system risk reports.
Client: Payvar Gohar Tejarat Company
Installed and commissioned power distribution systems for lighting and ventilation.
Conducted load testing to ensure stable power delivery and operational efficiency.
Integrated grounding systems and surge protection for warehouse equipment.
Safety During Maintenance: Developing and implementing safe methods for conducting maintenance activities.
Infrastructure Improvement: Upgrading electrical infrastructure to enhance efficiency and reduce operational issues.
Client: Sadaf Abi Bandar Company
Protective System Tests: Evaluating the performance of protective systems to ensure the safety of electrical systems.
Employee Training: Conducting training courses for staff on electrical safety and handling emergency situations.
Sadaf Abi Bandar Project
Upgraded electrical wiring and power systems to meet updated safety codes.
Installed modern lighting systems and repaired damaged wiring for uninterrupted power supply.
Collaborated with contractors to integrate electrical systems with building designs.
Client: Nasim Sahar Khalij Fars Company
Installed and maintained overhead electrical lines and infrastructure for rail signaling systems.
Conducted high-voltage inspections and ensured compliance with safety standards.
Designed and integrated power supply systems with rail communication equipment.
Client: Faradast Energy Flat Company
Project Location: Jofeir
Installed and managed temporary power systems for construction and piping operations.
Coordinated with mechanical teams to ensure compatibility between electrical systems and gas processing units.
Conducted safety audits and monitored equipment performance for energy efficiency.